135 Using the cumulative cost curve in the special window, height B representsA. actual cost to dateB. total budgeted costs for the projectC. planned cost for month 6D. cost varianceE. earned value

题目内容(请给出正确答案)

135 Using the cumulative cost curve in the special window, height B represents

A. actual cost to date

B. total budgeted costs for the project

C. planned cost for month 6

D. cost variance

E. earned value

参考答案和解析
正确答案:B
如果没有搜索结果或未解决您的问题,请直接 联系老师 获取答案。